Estimate video review capacity for each person who must approve the work, then compare their workload with the time they can actually reserve before the deadline. Add up the edits, review passes, final exports and time needed to consolidate feedback. A total team-hours figure can hide a bottleneck: spare time with one reviewer does not resolve a shortfall with the person who must verify the claims.
The worksheet below helps a marketing or communications lead decide whether to commission the proposed set of videos, reduce it or arrange more review capacity. It is a planning exercise, not a claim about how quickly Bolt or any client reviews videos.
Start with outputs and named people
List the original edits and the versions made from each one. Separate a crop of an approved sequence from an edit that changes the opening, wording or demonstration. Bolt’s guide to planning meaningful video variations helps make those differences explicit.
For every output, record who checks the story and claims, who checks brand and presentation, and who checks the actual delivery file. One person may hold several responsibilities. Attach each row to a real person rather than an unnamed department, and count that person’s available time only once.
Use a pilot to estimate the work
Ask each reviewer to time a representative review, including watching, replaying, checking references and writing useful notes. Record the kind of cut reviewed. A first story review and a final caption check are different tasks, so do not use one timing for both.
For each row, calculate: number of items × planned passes × minutes per item per pass = estimated working minutes. Add separate time for consolidating notes and resolving conflicting requests. If review tasks vary substantially, give them separate rows.
Reserve actual calendar blocks with each person. “Available this week” is too vague when the cut arrives after their only free afternoon. Confirm the supplier’s revision scope and response windows separately; the number of passes in your worksheet is an assumption to discuss, not an entitlement to extra revisions.
A worked example: enough total time, one overloaded reviewer
Imagine a fictional campaign with three original edits and nine derived versions, making twelve final exports. The derived versions preserve the approved meaning. For this example, the original-edit owner checks story, claims and brand direction; another reviewer checks presentation in the derived versions. Every final export also receives a delivery check.
All timings below are invented to demonstrate the calculation. Replace them with timings from your own pilot. In particular, three minutes is not a recommended or sufficient final-check allowance for every video.
| Assigned responsibility | Calculation | Work | Reserved time |
|---|---|---|---|
| Original story and claims owner | 3 edits × 2 passes × 12 | 72 | 60 |
| Derived-version brand reviewer | 9 versions × 1 pass × 4 | 36 | 45 |
| Final delivery checker | 12 exports × 1 pass × 3 | 36 | 45 |
| Feedback coordinator | 2 sessions × 15 | 30 | 30 |
| Total | 174 | 180 |
The total suggests six minutes of spare capacity. But the original story and claims owner needs 72 minutes and has reserved only 60. That twelve-minute shortfall still needs a decision. The brand reviewer’s nine spare minutes and delivery checker’s nine spare minutes cannot supply an approval they do not own.
First ask whether the required owner can reserve more time before the dependent reviews begin. If another qualified person can take part, agree their responsibility and allow for briefing them. Do not silently remove a required check to make the arithmetic fit.
Compare a smaller release before approving the full scope
Suppose the campaign can release two original edits and six derived versions first. Using the same illustrative assumptions, the four workloads become 48, 24, 24 and 30 minutes: 126 minutes in total. Each now fits the same person’s reserved time.
That gives the commissioning team a concrete alternative: defer one original and its three derived versions, or secure enough review time for the larger release. Check that the smaller set still answers the campaign’s audience question. Reducing outputs is useful only if the remaining work serves its intended purpose.
If one person handles both original review and coordination, combine those rows. In the larger example, that person needs 102 minutes. Do not give them a separate capacity allowance for each job unless those are genuinely different reserved blocks.
Do not confuse working time with a release date
After the workload fits, place the reviews in sequence. Record when the edit arrives, when the owner can review it, when consolidated notes return and when the editor can supply the next version. A workable total does not establish a workable calendar.
Approval must remain attached to the exact version. A derived cut that changes a claim, caption meaning, narration or demonstration needs the relevant factual review too. Add that work to the worksheet. Final checks still cover every delivered export, including its captions and destination requirements.
For the decision process around those checks, use Bolt’s video approval guide. If this is ongoing work, carry the measured review timings into your recurring video production plan and revisit them when the subjects or formats change.
Copy these fields into your production plan
Use one row per person and task: output IDs; review responsibility; named owner; item count; planned passes; measured minutes per item; total working minutes; reserved calendar blocks; shortfall; decision. Keep the timing source beside the estimate, such as a pilot cut and review date. Mark an unmeasured assumption clearly.
Before commissioning, resolve each shortfall by reserving time, assigning a qualified reviewer or reducing the release scope. Then agree the sequence and revision arrangement with the production team.